Energy audits: obligations and implementation

Directive (EU) 2023/1791 on energy efficiency strengthens obligations for companies. It rests on two thresholds of average annual energy consumption: about 10 TJ for an energy audit and about 85 TJ for an energy management system.

Updated on

What the directive requires

  • Energy audit every four years for companies above the 10 TJ threshold, unless they hold a certified management system.
  • Energy management system above 85 TJ, for example under ISO 50001.
  • Implementation plan for cost-effective recommendations, with some information published depending on national transposition.

Content of a quality audit

An audit following EN 16247-1 or ISO 50002 relies on measured data, a balance by use and an analysis of savings quantified in energy, cost and emissions. It covers buildings, processes and transport, and ranks actions by payback. National transposition applies to large companies on headcount and turnover criteria: check the thresholds that apply to your entity.

  • Collect bills, load curves and production data.
  • Install temporary metering if sub-metering is missing.
  • Model savings: compressed air, cooling, steam, recoverable heat.
  • Prioritise with a financial method such as EN 17463.

Turning the audit into results

An audit is only worth it if actions follow. Assign an owner per saving, budget the first actions and track gains with indicators. A heat pump or storage identified by the audit then gets a full feasibility study, and available subsidies are covered in the article on investment and public policy.

Preparing for the deadline

Compute your three-year average consumption to see which threshold applies. If an audit is required, plan it early enough to have representative measurements over at least one full season, and keep proof of recommendation follow-up in case of inspection.

Skills and resources

Auditors should be independent of the audited processes and hold recognised competence in industrial systems. Internal teams can lead the audit if they meet the same independence and quality requirements. Budget the audit as a project, with data collection time from maintenance and production, rather than as a paperwork exercise.